To estimate a wood fence the way our fence calculator does, divide the fence length by the post spacing and round up to get sections; a straight run needs one more post than it has sections, and each section needs its own set of rails. For pickets, divide the fence length in inches by the picket width plus any gap. A 100 ft straight fence with posts 8 ft apart needs 14 posts, 26 rails (two per section), and 230 pickets 5.5 inches wide with 5 percent extra.

Enter your run below. Add posts for every corner, end, and gate, as explained in the steps.

How many fence posts and pickets do you need?

For a straight run of picket fence. Results include posts, rails, pickets, and concrete.

ft
ft
rails
in
in
bags
%

Add a post for every corner, end, and gate opening. Rails are assumed to be at least as long as the post spacing.

How to measure for a fence

  1. Call 811 first. 811 is the free national call-before-you-dig service. Contact it a few business days before you dig so buried utility lines can be marked with paint or flags.
  2. Confirm the line and the rules. Know where your property line is, and check local zoning or HOA rules for fence height, setbacks, and permits before you buy materials.
  3. Measure each straight run separately. Stake the corners and run a string line. Measure each straight side in feet. The calculator handles one straight run at a time.
  4. Mark corners, ends, and gates. Each corner, each end, and each side of a gate opening needs a post. When two runs meet at a corner, they share that post, so subtract one post per shared corner when you add runs together.
  5. Choose post spacing. Lowe's fence estimating guide uses posts every 8 ft on center, and also lists 6 ft sections. Your rails must be at least as long as the spacing.
  6. Measure the actual picket width. Lumber is sold by nominal size. A 1x6 board actually measures 3/4 × 5-1/2 inches, according to the Southern Pine Inspection Bureau, which is why the calculator defaults to 5.5 inches.
Parts of a wood fence: posts, rails and picketsElevation of three fence sections seen from the rail side. Posts are 8 feet apart on center and set in concrete, each section has 2 rails, and 5.5 inch pickets run edge to edge with no gap.FENCE PARTS: POSTS, RAILS, PICKETSPost2 rails per sectionPickets, 5.5 in wideConcrete,2 bags per post8 ft on centerAssumes rails at least as long as the post spacing.
A section is the span between two posts: here posts sit 8 ft on center in 2 bags of concrete each, carrying 2 rails and 5.5 in pickets.

The fence formula

The calculator uses:

  • Sections = fence length ÷ post spacing, rounded up
  • Posts = sections + 1
  • Rails = sections × rails per section
  • Pickets = (fence length × 12 ÷ (picket width + gap), rounded up) × (1 + extra % ÷ 100), rounded up again
  • Concrete bags = posts × bags per post, rounded up

This matches the method in Lowe's fence estimating guide, which divides the fence length in inches by the actual picket width plus spacing.

Worked example (the calculator's default values)

A straight 100 ft fence with posts every 8 ft, 2 rails per section, 5.5 in pickets with no gap, 2 bags of concrete per post, and 5 percent extra pickets:

  1. Sections: 100 ÷ 8 = 12.5, rounded up to 13
  2. Posts: 13 + 1 = 14
  3. Rails: 13 × 2 = 26
  4. Pickets: 1,200 in ÷ 5.5 = 218.2, rounded up to 219; plus 5 percent = 229.95, rounded up to 230
  5. Concrete: 14 × 2 = 28 bags

The calculator shows: "You need 14 posts, 26 rails, and 230 pickets. 13 sections of up to 8 ft for a 100 ft straight run, and about 28 bags of concrete to set the posts."

Because 100 isn't evenly divisible by 8, one section ends up shorter, or you can space all 13 sections evenly at about 7.7 ft.

Example: a fence on three sides of a yard

Say you fence a backyard with runs of 50, 100, and 50 ft, and the two side runs meet the long run at corners. Running each side through the calculator gives 8 + 14 + 8 = 30 posts. The two corners are shared, so the real total is 28 posts. Pickets for the three runs are 116 + 230 + 116 = 462.

Counting fence posts, rails and pickets for 100 feetA 100 foot fence drawn over a tape measure with posts every 8 feet: 13 sections, the last one only 4 feet long, and 14 posts. With 2 rails per section that is 26 rails, plus 230 pickets and 28 bags of concrete.100 FT OF FENCE: 13 SECTIONS, 14 POSTS12345678910111213081624324048566472808896100feetSection 13 is only 4 ft14 posts = 13 sections + 1Sections: 100 ft ÷ 8 ft = 12.5 → 13 sectionsPosts: 13 + 1 = 14 posts · Rails: 13 × 2 = 26 railsPickets: 1,200 in ÷ 5.5 in = 218.2 → 219, + 5% = 230Concrete: 14 posts × 2 bags = 28 bagsAdd a post for every corner, end, and gate opening.
A straight 100 ft run at 8 ft spacing needs 13 sections and 14 posts, which works out to 26 rails, 230 pickets, and 28 bags of concrete.

Pickets per 8 ft section

Picket widthGapPickets per 8 ft sectionPickets per 100 ft (no extra)
5.5 inNone (privacy)18219
5.5 in1/2 in16200
5.5 in2 in13160
3.5 inNone (privacy)28343
3.5 in1.5 in20240
3.5 in3.5 in14172

Counts are rounded up per section. The 5.5 in pickets with a 2 in gap match the spacing example in Lowe's guide (7.5 inches per picket plus space).

Rails, post depth, and holes

ItemGuidelineSource
Rails, 4 ft tall fence2 per sectionLowe's fence guide
Rails, 6 ft tall fence3 per sectionLowe's fence guide
Post hole diameterAbout 3 times the post width (about 10.5 in for a 4x4, which measures 3.5 in)Quikrete
Post hole depth1/3 to 1/2 of the post height above ground (at least 2 ft for a 6 ft fence)Quikrete
Gravel at hole bottomAbout 6 in, compactedQuikrete

Frost depth and local code can require deeper holes, so check with your building department. For tall fences or windy, exposed sites, a fence contractor can confirm post size and depth.

How much concrete per fence post?

The calculator defaults to 2 bags per post, but the right number depends on your hole. Quikrete's data sheet for 50 lb Fast-Setting Concrete Mix gives a yield of about 0.375 cu ft per bag and says two bags will set a 3 in square post in a 9 in diameter hole 30 inches deep.

Hole width matters more than most people expect, because the volume grows with the square of the diameter. A 4x4 post actually measures 3.5 × 3.5 in, so Quikrete's "3 times the post width" rule gives a hole about 10.5 in across. Scaling from Quikrete's two-bag figure, that hole takes roughly 3 bags at 30 inches deep. A 12 in hole holds nearly twice as much concrete as the 9 in hole, or about 4 bags. Set the bags-per-post field to 3 and the example fence needs 42 bags instead of 28; at 4 bags it needs 56.

Quikrete's post-setting guide, which pours the dry mix into the hole and then adds water, calls for about a gallon of water per 50 lb bag, filling the hole to 3 to 4 inches below ground, and waiting about 4 hours before putting heavy loads on the posts. The mix sets in 20 to 40 minutes. For the gravel layer, Quikrete's shopping list for the job includes 50 lb bags of All-Purpose Gravel.

Tips for buying fence materials

  • Order extra pickets. Lowe's recommends increasing the picket count by 10 percent. The calculator defaults to 5 percent; raise it if you expect to cull warped or split boards.
  • Buy rails at least as long as your spacing. With 8 ft on center, 8 ft rails span post to post.
  • Plan the gates first. If you buy a prebuilt gate, subtract the opening from the length you enter for pickets. If you build the gate from the same pickets, leave it in.
  • Count hardware. Lowe's guide lists one post cap per post. Gates need their own hardware, and fasteners depend on your rail and picket count.
  • Use the actual picket width. Measure a board at the store. A small difference adds up over 100 feet.

Common mistakes to avoid

  • Forgetting extra posts. Each corner, end, and gate side needs one.
  • Double-counting shared corners when you add up several runs.
  • Using nominal picket width. A "1x6" is 5.5 inches wide, not 6.
  • Undersizing concrete. Wider holes take far more concrete than the 2 bag rule of thumb.
  • Digging before utilities are marked. Call 811 a few business days ahead.

Frequently asked questions

How many fence posts do I need for 100 feet?

For a straight run, 14 posts at 8 ft spacing or 18 posts at 6 ft spacing. Add posts for gates, and remember that corners are shared between runs.

How far apart should fence posts be?

Lowe's fence estimating guide uses 8 ft on center, and 6 ft sections are also common. Closer spacing means more posts and concrete but shorter spans for the rails.

How many pickets are in an 8 ft fence section?

With 5.5 in pickets and no gap, about 18. With a 1/2 in gap, 16. With 3.5 in pickets and no gap, 28.

How many bags of concrete do I need per fence post?

Quikrete says two 50 lb bags of Fast-Setting Concrete Mix set a 3 in post in a 9 in hole 30 inches deep. For a 4x4 in a hole three times its actual width (about 10.5 in), plan on roughly 3 bags at that depth, and about 4 bags in a 12 in hole.

How deep should fence posts be?

Quikrete's post-setting guide says 1/3 to 1/2 of the post's height above ground, which is at least 2 ft for a 6 ft fence. Check local frost depth and code requirements too.

How many rails does a fence need?

Lowe's guide uses 2 rails per section for a 4 ft fence and 3 rails per section for a 6 ft fence.